How to close packages

Risposte di colloquio

Anonimo

5 set 2017

Received packages, Line checking, Story of fit up reports, Welding reports, NDE reports and Punch reports...

Anonimo

6 set 2017

Well, i'll assume we are talking about piping test packages in here...Once we receive the package the line will be check,soon a punchlist will come out,indicating those balance work to be done before and after testing. Say for example, a welded joint balance or a temporary gasket,all missing accessories down to the smallest one..